Anatomy of a blown budget
BART-to-SJ proves to be a construction contract without an effective price ceiling.
One of the most troubling revelations concerns VTA's amended agreement with Kiewit Shea Traylor (KST), the contractor responsible for the BART-to-SJ project's five-mile tunnel and trackwork.
Instead of negotiating a conventional fixed-price contract, VTA agreed to a target-price arrangement that its independent engineering consultant, Gall Zeidler, says leaves the agency responsible for potentially unlimited allowable reimbursable costs.
Of the contract's $110 million in fees subject to performance incentives, only $45 million is specifically tied to controlling costs. The remainder concerns schedule performance and other measures.
Gall Zeidler identified nine critical contract risks, including the absence of a binding ceiling on reimbursable costs. Although the contract contains cost-sharing provisions, the consultant concluded that VTA bears most of the financial exposure from major overruns.--Mark Joffe on X
Read more
Because it's never too much
In 2014, VTA estimated the BART-to-SJ extension would cost $4.7 billion and be finished by the end of 2026. By the 2024 groundbreaking, the estimate was $12.7 billion, and the target date is now 2037. SJ Mayor Mahan asked what else VTA could be doing so it wouldn’t be back in a year or two with “a whole new number.” Better estimates are useful, but they don’t answer the question of how much is too much. So far, no number has been high enough to stop the project.--Mark Moses, author of the The Municipal Financial Crisis
Follow Opportunity Now on Twitter @svopportunity
We prize letters from our thoughtful readers. Typed on a Smith Corona. Written in longhand on fine stationery. Scribbled on a napkin. Hey, even composed on email. Feel free to send your comments to us at opportunitynowsv@gmail.com or (snail mail) 1590 Calaveras Ave., SJ, CA 95126. Remember to be thoughtful and polite. We will post letters on an irregular basis on the main Opp Now site.